USG Taylor Way Plant Site cleanup: environmental determination issued
The cleanup addresses arsenic and lead contamination in soil and groundwater across four areas of the site, including excavation, installation of a funnel and gate permeable reactive barrier (PRB), and soil capping. After comments close on December 18, state rules let the lead agency keep, change or withdraw the determination.
Comments on or before
The record
- Record
- SEPA 202604805 from Washington Department of Ecology
- Filed as
- Environmental review (SEPA)
- Where
- 2301 Taylor Way, Tacoma
- Project name
- USG Interiors, LLC (USG) Taylor Way Plant Site Cleanup Action
- Property owner
- LLC and The Port of Tacoma
- Submitted
- November 13, 2026
- Status
- Decision Issued (Nov 13, 2026)
What the status means. The agency has published its decision on this application. A land-use or environmental decision is not a building permit. The status is the agency’s, as of the date shown; the record has where it stands today.